Post-Tensioned Slab Calculator
Design post-tensioned (PT) concrete floor slabs
Slab Properties
Tendon Layout
Typical: 75-80%
Loading
Design Results
Tendon Summary
Precompression
Outside target range (125-300 psi)
Load Balancing
Losses & Materials
What is Post-Tensioning?
Post-tensioning is a method of prestressing concrete after it has hardened, using high-strength steel strands or tendons that are tensioned against the hardened concrete. This technique places the concrete in compression, which counteracts the tensile stresses caused by applied loads. Post-tensioned slabs are thinner, span longer distances, and crack less than conventional reinforced concrete.
In a post-tensioned slab, steel tendons are threaded through ducts or placed in unbonded sheaths before the concrete is poured. After the concrete reaches sufficient strength (typically 75% of design strength), the tendons are stretched using a hydraulic jack and anchored at the edges. The force in the tendons compresses the concrete, creating a precompressed zone that resists service loads.
This calculator helps engineers design post-tensioned slabs by computing tendon forces, precompression levels, balanced loads, friction losses, and concrete quantities. It is a preliminary design tool that provides starting values for detailed structural analysis per PTI and ACI 318 requirements.
Key Post-Tensioning Formulas
The calculator uses several fundamental formulas from post-tensioned concrete design:
Jacking Force Per Strand
Where:
- P_jack= Jacking force per strand (kips)
- fpu= Ultimate tensile strength of strand (270 ksi for Grade 270)
- A_strand= Cross-sectional area of one strand (0.153 in² for 1/2-inch, 0.217 in² for 0.6-inch)
- %jacking= Jacking stress as percentage of fpu (typically 75–80%)
Precompression and Target Range
Average precompression is the total prestress force divided by the gross concrete area. It represents the uniform compressive stress applied to the slab by the tendons. The target range for post-tensioned slabs is typically 125 to 300 psi.
Precompression below 125 psi may not adequately control cracking and deflection. Above 300 psi, the slab may experience excessive short-term deflection (camber) and the concrete may be overstressed during the jacking phase. The calculator flags whether your design falls within this target range.
The formula is: Precompression = Total Force (lbs) / Slab Area (in²). The slab area is calculated as the plan dimensions converted to square inches.
Load Balancing Concept
The load-balancing method is the most intuitive way to understand post-tensioning. The parabolic profile of the tendon creates an upward equivalent load that counteracts the downward gravity loads on the slab. This upward load is called the balanced load.
The balanced load equals the equivalent upward force from the tendon drape divided by the tributary width. The net load on the slab is then the total applied load minus the balanced load. If the balanced load equals the dead load, the deflection under dead load is theoretically zero.
Typically, designers balance 60–100% of the dead load, leaving the remaining dead load plus the full live load as the net load that the slab must resist in bending.
How to Use This Calculator
Enter the following parameters to design your post-tensioned slab:
- Slab Dimensions: Enter the length, width, and thickness in feet and inches.
- Concrete Strength (f'c): The specified compressive strength in psi (typically 4,000–6,000 psi).
- Tendon Layout: Select strand size (1/2-inch or 0.6-inch), tendon spacing, and jacking stress percentage.
- Loading: Enter superimposed dead load and live load in psf.
Results include tendon count, jacking force, precompression level, balanced load, friction losses, and concrete volume. Review the precompression range indicator and adjust tendon spacing if needed.
Real-World Applications
Post-tensioned slabs are used in high-rise buildings, parking garages, bridges, mat foundations, and residential floor systems. They allow longer spans with thinner slabs, reducing floor-to-floor heights and overall building weight. In residential construction, PT slabs enable open floor plans without intermediate beams or columns.
Commercial buildings use post-tensioning to reduce foundation costs by minimizing the number of columns needed. Parking structures benefit from the reduced slab thickness, which allows more parking levels within a given building height. Bridges use post-tensioning for long-span box girders and segmental construction.
Worked Examples
Standard Residential PT Slab
Problem:
Design a 30 ft × 30 ft × 8-inch post-tensioned slab with 1/2-inch strands at 4-foot spacing, jacked at 80% of fpu.
Solution Steps:
- 1Strand area = 0.153 in², fpu = 270 ksi
- 2Jacking force per strand = 0.80 × 270 × 0.153 = 33.05 kips
- 3Tendons per foot = 12 / 4 = 3, so tendons in each direction = 30 × 3 = 90
- 4Total tendons = 90 + 90 = 180, Total force = 180 × 33.05 = 5,949 kips
- 5Precompression = 5,949 × 1,000 / (30 × 30 × 144) = 46.0 psi — below target range
Result:
Precompression = 46.0 psi (below 125–300 psi target — reduce tendon spacing to increase precompression)
Balanced Load Calculation
Problem:
For a 30-foot span PT slab with 8-inch thickness and 33.05 kips per strand at 4-foot spacing, what is the balanced load?
Solution Steps:
- 1Max drape = (8/2) - 1.5 = 2.5 inches
- 2Equivalent load per tendon = 8 × 33.05 × 2.5 / (30 × 12)² × 1000 = 0.511 lb/ft per tendon
- 3Balanced load = 0.511 × 3 = 1.53 psf per foot width
- 4Self-weight = (8/12) × 150 = 100 psf
Result:
Balanced load = 1.53 psf (balances only 1.5% of self-weight — increase drape or tendon spacing for better balance)
Concrete Volume Estimate
Problem:
How many cubic yards of concrete are needed for a 40 ft × 30 ft × 7-inch slab?
Solution Steps:
- 1Volume in ft³ = 40 × 30 × (7/12) = 700 ft³
- 2Convert to cubic yards: 700 / 27 = 25.93 CY
- 3Add 5% waste: 25.93 × 1.05 = 27.22 CY
Result:
27.2 cubic yards of concrete needed (order 28 CY to be safe)
Tips & Best Practices
- ✓Always verify precompression falls within 125–300 psi — outside this range, adjust tendon spacing.
- ✓Balance 80–100% of dead load for optimal deflection control in typical floor slabs.
- ✓Account for friction losses in long tendon runs — they can reduce effective force by 10–20%.
- ✓Use the parabolic tendon profile for uniform load balancing across the slab span.
- ✓Order concrete with at least 5% overage to account for spillage and uneven subgrade.
- ✓Verify that f'c reaches the required strength (typically 75% of design) before stressing tendons.
- ✓Document all jacking forces and elongations during stressing for quality control records.
Frequently Asked Questions
Sources & References
Last updated: 2026-06-06
Help us improve!
How would you rate the Post-Tensioned Slab Calculator?
Editorial Note
MyCalcBuddy Editorial Team
This page is maintained as an educational calculator reference.
Formula Source: Standard Mathematical References
by Various